Beryllium Sub-Assembly
Joining the completed parts into the Beryllium Sub-Assembly
(Cornell drawing 6058-026 REV A) will be done by the vendor.
This task includes electron beam welded joints between the Inner Central Skin
(6058-029 REV A) and the Central Manifold Ends (6058-031 REV A), electron
beam welded joints between the Outer Central Skin (6058-030 REV A)
and the Central Manifold Ends (6058-031 REV A),
and braze joints between the End Collars (6058-032 REV A) and the Inner
Central Skin (6058-029 REV A) shown on Inner Central Skin/End Collar
Sub-Asm (6058-040). The following specifications cover this work.
- Approved Parts must be used.
- Dimensional Inspection of the completed assemblies to insure they
meet the tolerances on the drawings is the responsibility of the vendor. An
inspection report must be submitted to the technical contacts. This report
should state the nominal dimension, the allowed tolerance, the achieved
dimension, the measurement accuracy and the name or initials of the
person responsible for the measurement.
- Electron Beam Weld Joint Design must allow for subsequent heating
of the part to 300°C without damage. The part will be subjected to this
temperature range during the gold coating process at Cornell.
- Braze Material and Braze Joint Design must allow for subsequent
heating of the part to 300°C without damage. The part will be
subjected to this temperature range during the gold coating process at Cornell.
The End Collar (6058-032 REV A) to Inner Central Skin (6058-029 REV A) joint
must be compatible with UHV. Radiation length of the braze material is
NOT an issue for these joints.
- Cleaning of the assembly after brazing and welding, but before
pressure and leak testing is the responsibility of the vendor.
- Pressure and Leak Testing of the assembly will be performed by the
vendor with a representative from Cornell present. The pressure test will
be performed with the inside at 1 Atmosphere and the cooling
channels between the Inner Central Skin (6058-029 REV A) and the
Outer Central Skin (6058-030 REV A) at 3 Atmospheres. The vacuum leak
test will be performed with the
inside of the beam pipe under vacuum and the outside and cooling channel
at one atmosphere. In this condition a mass spectrometer leak test must
show no leakage higher than 2 x 10-10 ATM CC/sec of Helium.
Last modified: Wed Jan 17 17:23:33 EST 2001